Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Arbitration — Partial Setting Aside
Delhi High Court · 28 September 2026

Severing the Bad From the Good: Price Variation Claim Revived as Award Is Partially Set Aside

In Dwarika Projects Ltd. v. New Okhla Industrial Development Authority (O.M.P.(COMM) 182/2019), the High Court held the arbitrator’s rejection of a price variation claim patently illegal for misreading the contract, set aside that part alone, and remitted the quantum to fresh arbitration while preserving the rest of the award.

Section 34 of the Arbitration and Conciliation Act, 1996 is usually described as an all-or-nothing jurisdiction. Increasingly, though, courts sever the offending portion of an award and leave the rest standing — provided the good and the bad are genuinely separable. A Delhi High Court judgment of 28 September 2026 is a textbook illustration: one claim’s rejection was annulled for patent illegality and sent back for quantification, while the awarded claims survived untouched.

The dispute in outline

Dwarika Projects built a bridge for NOIDA under a contract of roughly Rs. 18.09 crore. Scheduled completion of December 2010 slipped to May 2012. In the arbitration that followed over the final bill, the sole arbitrator’s award of 10 December 2018 allowed Claims 1 and 3 (about Rs. 1.03 crore) but rejected Claim 4 — price variation of about Rs. 2.29 crore. The contractor challenged the rejection under Section 34; the matter was decided by Justice Mini Pushkarna on 28 September 2026.

Where the arbitrator went wrong

The qualifying words were ignored. Clause 50.1 fixed rates but expressly “barring adjustment (which may be plus or minus) to be made as provided for herein.” Treating the rates as immutable required deleting that language — a misreading, not a permissible construction.
Extension did not extinguish entitlement. Clauses 51.2 and 7.5, read together, showed that price variation continued into the extended period even where the delay lay at the contractor’s door; what changed was the computation method.
Patent illegality followed. An award that contradicts the contract’s express terms offends Section 28(3) and falls within the patent illegality ground in Section 34(2A) for domestic awards.

The remedy: surgical, not wholesale

The Court did three things, and the combination is what makes the judgment notable:

Set aside the rejection of Claim 4

The price variation claim was revived — for both the original and the extended contract period.

Remitted quantum to fresh arbitration

Because a Section 34 court cannot itself compute and award the amount, quantification under the contractual formula goes back to arbitration.

Preserved the remainder

The allowed claims, the delay-attribution findings on issues like electrical poles and steel sourcing, and the cost directions survived: they were plausible findings independent of the severed part.

Severability is the quiet doctrine here. Where distinct claims rest on distinct reasoning, annulling one need not doom the rest — sparing parties a complete re-arbitration of matters correctly decided.

Price variation clauses: the recurring battlefield

Clause patternLitigation risk
Fixed rates with adjustment carve-outsTribunals reading “fixed” absolutely — the error corrected in this case
Variation during extended periodsConfusing entitlement with computation where delay is contractor-attributable
Indexed formulasDisputes over base indices and notification dates — draft with worked examples

Takeaways

For contractors: a rejected claim is not necessarily dead — where the tribunal’s reading defies the clause, Section 34 offers a real, targeted remedy. For employers: resist over-broad defences that invite tribunals to rewrite rate clauses; the correction, when it comes, is expensive. For both: plead severability expressly, so that a successful challenge does not unravel the parts of the award each side can live with.

This article is for general information only and is not legal advice. Section 34 challenges carry strict limitation; parties should obtain advice on their own matter.

Frequently Asked Questions

What was the contract and the dispute?

A bridge construction contract of about Rs. 18.09 crore awarded by NOIDA. The work, due in December 2010, was completed in May 2012 after delays. The sole arbitrator’s award of December 2018 allowed two claims totalling about Rs. 1.03 crore but rejected the contractor’s price variation claim of about Rs. 2.29 crore.

Why was the rejection of price variation “patently illegal”?

The arbitrator read the rate clause as fixing prices absolutely, ignoring its own qualifying words — “barring adjustment (which may be plus or minus) to be made as provided for herein.” The contract expressly contemplated price variation; a construction that erases express language is not interpretation but misreading, attracting Section 34(2A).

Did delay by the contractor defeat price variation for the extended period?

No. Reading the relevant clauses together, the Court held price variation remained payable even where the extension was attributable to the contractor — the clauses changed the method of calculation for the extended period, not the entitlement itself.

What happens next?

The question of quantum of price variation goes to fresh arbitration under the applicable formula. The rest of the award — the allowed claims and costs — stands, since the severed portion was independent of them.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 29 September 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.