Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Commercial — Concession Disputes
Delhi High Court · 28 September 2026

Tribunals Interpret, They Do Not Rewrite: The Total Project Cost Ceiling Holds in NHAI Concession Dispute

In Kurukshetra Expressway Pvt. Ltd. v. National Highways Authority of India (FAO(OS)(COMM) 211/2026), a Division Bench upheld the partial setting aside of an arbitral award that had computed termination payment on an enlarged project cost, holding the tribunal bound by the contractually defined ceiling.

Infrastructure concession agreements are dense, negotiated codes: definitions carry money, and few definitions carry more than “Total Project Cost.” When a concessionaire terminates and claims termination payment, that defined figure often decides hundreds of crores. A Delhi High Court judgment of 28 September 2026 confirms that an arbitral tribunal which departs from such a definition does not commit a mere error of interpretation — it commits patent illegality, and the award falls to that extent.

The commercial background

The appellant concessionaire contracted with NHAI to four-lane a highway stretch on a Design, Build, Finance, Operate and Transfer basis. Toll collection — the concessionaire’s revenue stream — was suspended for a prolonged period during a farmers’ agitation, compounded by the pandemic. The concessionaire terminated the agreement and sought termination payment exceeding Rs. 1,347 crore. A three-member arbitral tribunal awarded Rs. 911.13 crore.

NHAI challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The single judge set aside the two principal claims, holding the computation had to respect the agreement’s definition of Total Project Cost — Rs. 650 crore. The concessionaire appealed under Section 37.

The Division Bench’s holding

Justices Anil Kshetarpal and Shail Jain dismissed the appeal on 28 September 2026, affirming the partial setting aside. Three propositions anchor the judgment:

The definition was a ceiling

The concession agreement defined Total Project Cost, and the termination payment formula was keyed to it. The definition operated as an express contractual limit on the tribunal’s computation.

The disaggregation letter could not enlarge it

The tribunal’s reliance on a disaggregation letter to lift the figure from Rs. 650 crore to Rs. 1,045.55 crore impermissibly displaced the negotiated definition with extrinsic material.

Rewriting is patent illegality

A tribunal may interpret ambiguous language; it may not reconstruct the bargain. Crossing that line takes the award outside permissible arbitral latitude and into Section 34(2A) territory.

The doctrinal frame

GroundScopeApplication here
Interpretation of ambiguous termsTribunal’s plausible view protectedNot this case — the term was defined
Patent illegality (S. 34(2A))Illegality going to the root, on the face of the award; domestic awards onlyEngaged — defined ceiling overridden
Ignoring contract terms (S. 28(3))Tribunal must decide in accordance with the contractReinforced the conclusion

The award was not annihilated wholesale. The offending claims were severed and the payment capped by reference to the contractual figure — an approach consistent with the growing acceptance of partial setting aside where good and bad parts of an award are separable.

What contract and disputes teams should take away

Definitions are the battlefield. In concession and EPC disputes, quantification usually turns on defined terms. Treat them at drafting stage as the caps and floors they will later become.
Extrinsic material has limits. Correspondence and cost break-ups can explain a contract; before a tribunal they cannot amend it.
Frame Section 34 challenges surgically. Identify the precise term the tribunal overrode. Courts respond to demonstrated reconstruction, not to general dissatisfaction with the result.

The judgment strengthens predictability in public-infrastructure arbitration: the bargained ceiling holds, however sympathetic the claimant’s losses. Risk events like toll suspensions must be addressed through the contract’s own mechanisms, not through award-stage enlargement of defined costs.

This article is for general information only and is not legal advice. Award challenges are strictly time-bound; parties should obtain advice on their own matter.

Frequently Asked Questions

What was the dispute?

A concessionaire engaged under a DBFOT model concession agreement for four-laning a highway terminated the agreement after prolonged toll suspension during a farmers’ agitation and the COVID-19 period, and claimed termination payment of about Rs. 1,347.53 crore. The arbitral tribunal awarded roughly Rs. 911.13 crore.

What happened in the Section 34 challenge?

The single judge set aside the principal claims, holding that the termination payment had to be computed on the contractually defined Total Project Cost of Rs. 650 crore, not the enlarged figure of about Rs. 1,045.55 crore which the tribunal had accepted on the strength of a disaggregation letter.

Why did the Division Bench agree?

Because the contract supplied an express ceiling. By displacing the defined figure through extrinsic material, the tribunal effectively rewrote the bargain — conduct outside the latitude allowed to arbitrators and squarely within the “patent illegality” ground under Section 34(2A) for domestic awards.

Does this weaken arbitration?

No. Courts continue to defer to plausible interpretations of ambiguous terms. The line crossed here was different: an unambiguous, defined term was overridden. Deference protects interpretation, not reconstruction.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 29 September 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.