you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Arbitration: Section 9
Delhi High Court · 23 November 2026

Section 9 Relief Is a Bridge, Not a Destination: The 45-Day Condition

A financier’s interim protection continues only if it commences arbitration within 45 days — after which the tribunal, not the court, holds the interim jurisdiction.

In Axis Finance Ltd v. Shri Onkar Power Tools & Ors., O.M.P.(I) (COMM.) 480/2026, decided on 23 November 2026, the Delhi High Court (Mr. Justice Om Prakash Shukla) disposed of a petition under Sections 9 and 17 of the Arbitration and Conciliation Act, 1996 with a structure every Section 9 practitioner should recognise: the interim arrangement continues for 45 days; the petitioner must commence arbitral proceedings within that window; the protection vacates automatically if it does not; and if arbitration begins, the relief continues only until the Arbitral Tribunal itself passes orders under Section 17. All contentions on maintainability and jurisdiction were left open.

The order in one view

Petition disposed of. The Section 9 petition by the financier against the borrower parties is disposed of at the threshold, not kept pending.
45 days to act. The petitioner must commence arbitral proceedings within 45 days of the order.
Automatic sunset. The interim arrangement continues for those 45 days and vacates automatically if arbitration is not commenced.
Handover to the tribunal. If arbitration is commenced, the interim relief continues until the Arbitral Tribunal passes orders under Section 17 — at which point the tribunal’s regime replaces the court’s.

The statutory design at work

The 2015 amendments rebuilt the relationship between courts and tribunals on interim relief. Section 9(2) prevents a party from obtaining pre-arbitration protection and then sitting on it: the measure is conditioned on actually starting the arbitration, within ninety days or the period the court fixes. Section 9(3) completes the design by making the tribunal, once constituted, the default forum for interim measures under Section 17 — court intervention thereafter requires showing that the tribunal’s remedy would be inefficacious. Section 17, in turn, gives the tribunal the same powers as a court under Section 9, with its orders enforceable as orders of the court. The present order compresses that entire architecture into a single disposal: protection now, arbitration promptly, tribunal thereafter.

Why courts prefer this structure

Disposing of a Section 9 petition with a commencement condition, rather than keeping it alive for months of affidavits, serves both sides. The applicant gets immediate protection — often the only thing that genuinely cannot wait. The respondent gets a guarantee that the protection cannot become a standing attachment divorced from any adjudication: if the applicant does not arbitrate, the relief dies of its own terms; if it does, the respondent’s objections on maintainability, jurisdiction and merits travel intact to the tribunal, which can modify or vacate the arrangement under Section 17. The court, for its part, avoids becoming the de facto case-management forum for a dispute the parties contracted to resolve elsewhere.

StageInterim forumGoverning provision
Before arbitration commencesCourtSection 9(1), disciplined by Section 9(2)
Tribunal constituted, arbitration pendingArbitral Tribunal (court only if S.17 relief inefficacious)Sections 9(3) and 17
Post-award, pre-enforcementCourtSection 9(1)

Practice notes

Diarise the fuse. A commencement condition is self-executing. Issue the Section 21 notice invoking arbitration well inside the window, and keep proof of service — commencement dates from the respondent’s receipt of the request.

For respondents, aim at Section 17. Where the court has left contentions open, the efficient battlefield is the tribunal’s first interim hearing, not a review of the Section 9 disposal.

Match the relief to preservation. Courts grant bridge relief readily when it preserves the status quo — assets, accounts, goods — and sparingly when it would amount to final relief in interim dress.

This note summarises an order of the Delhi High Court for general information and is not advice on any particular matter.

Frequently Asked Questions

What does Section 9 of the Arbitration Act allow?

Section 9 lets a party seek interim measures from a court before or during arbitral proceedings, or after the award but before enforcement — securing the amount in dispute, preserving assets or goods, appointing receivers, and similar protective relief.

What is the Section 9(2) time discipline?

Where a court grants an interim measure before the commencement of arbitral proceedings, Section 9(2) requires the arbitration to commence within ninety days of the order, or within such further or shorter time as the court fixes. In this case the Court fixed 45 days, with automatic vacation of the interim arrangement on default.

Why does the relief hand over to the tribunal?

Section 9(3) directs that once the Arbitral Tribunal is constituted, the court shall not entertain a Section 9 application unless remedies under Section 17 would be inefficacious. The scheme makes the tribunal the primary forum for interim measures during the arbitration, with court relief operating as a bridge until it is in place.

What happened to the respondents’ objections?

Nothing was decided against them. The order expressly leaves all contentions regarding maintainability and jurisdiction open — to be raised before the Arbitral Tribunal, which will take its own view under Section 17.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 25 November 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.