Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Section 9: Bank Guarantees
Delhi High Court · 26 November 2026

No Fraud, No Special Equities: Section 9 Petition Against Airport Bank Guarantee Encashments Dismissed

Encashment of guarantees worth about Rs 329 crore, including a Rs 100 crore advance bank guarantee, was held to raise purely monetary issues that arbitration can restitute — not irretrievable injustice that Section 9 must prevent.

In Tata Projects Limited v. Yamuna International Airport Private Limited & Ors., O.M.P.(I) (COMM.) 478/2026, decided on 26 November 2026, Justice Tushar Rao Gedela of the Delhi High Court dismissed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 arising out of the EPC contracts for Phase 1 of the Noida International Airport. The contractor sought restitution of bank guarantees already encashed — including an advance bank guarantee of Rs 100 crore — and protection for those yet unencashed. The Court declined, restating the narrow twin gateway of fraud and irretrievable injustice that governs interference with unconditional bank guarantees.

A marquee project, a familiar question

The contracts behind this petition are among the largest construction engagements in the National Capital Region: EPC packages of roughly Rs 1,892 crore and Rs 2,690 crore for the first phase of the Noida International Airport. When the relationship soured — claims of about Rs 1,113 crore on one side, counterclaims of about Rs 437 crore on the other, a Rs 500 crore settlement agreement in February 2026, and then encashments of about Rs 329 crore in guarantees — the contractor came to court under Section 9 seeking its money back and a freeze on the remaining retention guarantees.

The legal question, however, was the oldest one in bank guarantee litigation: when may a court stop, or undo, the encashment of an unconditional guarantee?

The twin gateway, applied

What the contractor argued
Special equities: the employer’s own conduct, including additional works and the timing of the invocations after the settlement, made the encashments inequitable and warranted restitution and protection of the unencashed guarantees.
→
What the Court held
No fraud was alleged at all. The encashments raise purely monetary issues, fully capable of restitution in arbitration if the invocations are found wrongful. Compensable monetary loss is not irretrievable injustice, and the merits of the invocations are for the arbitral tribunal, not a Section 9 court.

The Court followed the Division Bench’s recent restatement in Vishal Infrastructure and the Supreme Court’s consistent line that an unconditional bank guarantee is an independent commitment the beneficiary may call upon, with judicial interference confined to egregious fraud and irretrievable injustice. Finding neither, it dismissed the petition, leaving every substantive question — including the propriety of each invocation — to the tribunal yet to be constituted.

Practical lessons for contractors and employers

SituationPosition after this judgment
Guarantee already encashedRemedy is a money claim in arbitration; Section 9 restitution would be final relief in interim clothing
Guarantee yet to be encashedInjunction only on egregious fraud with bank’s notice, or genuine irretrievable injustice — commercial hardship does not qualify
Settlement agreement in the backgroundWhether encashment breaches the settlement is itself an arbitrable merits question, not a ground for interim restraint
Drafting stageIf the guarantee is unconditional, assume it will be paid on demand; negotiate conditions into the instrument, not into litigation later
This report summarises a judgment of the High Court of Delhi dated 26 November 2026 for general information. It is not legal advice, and it expresses no view on the disputes pending between the parties.

Frequently Asked Questions

What was the dispute about?

Yamuna International Airport Pvt. Ltd. awarded Tata Projects two EPC contracts dated 8 June 2022 for Phase 1 of the Noida International Airport, together worth about Rs 4,582 crore. Disputes over delays and payments followed — the contractor claimed about Rs 1,113 crore and the employer counterclaimed about Rs 437 crore — and a settlement agreement of 25 February 2026 provided a one-time payment of Rs 500 crore. The employer thereafter invoked bank guarantees worth about Rs 329 crore, including a Rs 100 crore advance bank guarantee encashed on 9 October 2026.

Why did the Court refuse relief?

The petitioner pleaded no fraud and rested its case on special equities. The Court held that none of the invocations and encashments, including the Rs 100 crore ABG, raised anything beyond purely monetary issues capable of restitution through the arbitral process. Monetary loss that arbitration can compensate is not irretrievable injustice, and the correctness of the invocations is a merits question for the tribunal.

What is the settled law on stopping bank guarantee encashment?

An unconditional bank guarantee is an independent contract between the bank and the beneficiary, and courts honour it save in two narrow situations: egregious fraud of which the bank has notice, and special equities in the form of irretrievable injustice. The Court followed the Division Bench in Vishal Infrastructure and the Supreme Court’s long line of authority to that effect.

Could restitution have been ordered under Section 9?

No. The Court observed that directing refund of encashed amounts at the interim stage would amount to granting final relief, which is beyond the scope of Section 9. The inquiry into whether the invocations were justified must await the arbitral tribunal.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 28 November 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.