In Tata Projects Limited v. Yamuna International Airport Private Limited & Ors., O.M.P.(I) (COMM.) 478/2026, decided on 26 November 2026, Justice Tushar Rao Gedela of the Delhi High Court dismissed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 arising out of the EPC contracts for Phase 1 of the Noida International Airport. The contractor sought restitution of bank guarantees already encashed — including an advance bank guarantee of Rs 100 crore — and protection for those yet unencashed. The Court declined, restating the narrow twin gateway of fraud and irretrievable injustice that governs interference with unconditional bank guarantees.
A marquee project, a familiar question
The contracts behind this petition are among the largest construction engagements in the National Capital Region: EPC packages of roughly Rs 1,892 crore and Rs 2,690 crore for the first phase of the Noida International Airport. When the relationship soured — claims of about Rs 1,113 crore on one side, counterclaims of about Rs 437 crore on the other, a Rs 500 crore settlement agreement in February 2026, and then encashments of about Rs 329 crore in guarantees — the contractor came to court under Section 9 seeking its money back and a freeze on the remaining retention guarantees.
The legal question, however, was the oldest one in bank guarantee litigation: when may a court stop, or undo, the encashment of an unconditional guarantee?
The twin gateway, applied
Special equities: the employer’s own conduct, including additional works and the timing of the invocations after the settlement, made the encashments inequitable and warranted restitution and protection of the unencashed guarantees.
No fraud was alleged at all. The encashments raise purely monetary issues, fully capable of restitution in arbitration if the invocations are found wrongful. Compensable monetary loss is not irretrievable injustice, and the merits of the invocations are for the arbitral tribunal, not a Section 9 court.
The Court followed the Division Bench’s recent restatement in Vishal Infrastructure and the Supreme Court’s consistent line that an unconditional bank guarantee is an independent commitment the beneficiary may call upon, with judicial interference confined to egregious fraud and irretrievable injustice. Finding neither, it dismissed the petition, leaving every substantive question — including the propriety of each invocation — to the tribunal yet to be constituted.
Practical lessons for contractors and employers
| Situation | Position after this judgment |
|---|---|
| Guarantee already encashed | Remedy is a money claim in arbitration; Section 9 restitution would be final relief in interim clothing |
| Guarantee yet to be encashed | Injunction only on egregious fraud with bank’s notice, or genuine irretrievable injustice — commercial hardship does not qualify |
| Settlement agreement in the background | Whether encashment breaches the settlement is itself an arbitrable merits question, not a ground for interim restraint |
| Drafting stage | If the guarantee is unconditional, assume it will be paid on demand; negotiate conditions into the instrument, not into litigation later |
Frequently Asked Questions
What was the dispute about?
Yamuna International Airport Pvt. Ltd. awarded Tata Projects two EPC contracts dated 8 June 2022 for Phase 1 of the Noida International Airport, together worth about Rs 4,582 crore. Disputes over delays and payments followed — the contractor claimed about Rs 1,113 crore and the employer counterclaimed about Rs 437 crore — and a settlement agreement of 25 February 2026 provided a one-time payment of Rs 500 crore. The employer thereafter invoked bank guarantees worth about Rs 329 crore, including a Rs 100 crore advance bank guarantee encashed on 9 October 2026.
Why did the Court refuse relief?
The petitioner pleaded no fraud and rested its case on special equities. The Court held that none of the invocations and encashments, including the Rs 100 crore ABG, raised anything beyond purely monetary issues capable of restitution through the arbitral process. Monetary loss that arbitration can compensate is not irretrievable injustice, and the correctness of the invocations is a merits question for the tribunal.
What is the settled law on stopping bank guarantee encashment?
An unconditional bank guarantee is an independent contract between the bank and the beneficiary, and courts honour it save in two narrow situations: egregious fraud of which the bank has notice, and special equities in the form of irretrievable injustice. The Court followed the Division Bench in Vishal Infrastructure and the Supreme Court’s long line of authority to that effect.
Could restitution have been ordered under Section 9?
No. The Court observed that directing refund of encashed amounts at the interim stage would amount to granting final relief, which is beyond the scope of Section 9. The inquiry into whether the invocations were justified must await the arbitral tribunal.