In National Highways Authority of India v. BSCPL Infrastructure Ltd., O.M.P.(COMM) 168/2016, decided on 23 November 2026, Justice Om Prakash Shukla of the Delhi High Court dismissed NHAI’s challenge to a majority award of 13 May 2015 granting the contractor Rs. 15,80,42,030 in prolongation costs for a 374-day overrun on the four-laning of NH-26 in Madhya Pradesh, with 10% interest compounded monthly from the invocation of arbitration.
The contract and the overrun
The April 2006 agreement — contract price Rs. 189.63 crore — required completion by 26 November 2008; the work finished on 5 December 2009. NHAI granted the 374-day extension of time without penalty or liquidated damages, a fact that anchored everything that followed: an employer who extends time without fault findings against the contractor concedes, at least prima facie, that the delay was not the contractor’s. The contractor claimed Rs. 40.33 crore under seven heads; the majority of the three-member tribunal awarded Rs. 15.80 crore across four — input costs (POL, cement, steel, bitumen), extended plant and equipment, and site and head-office overheads — while rejecting financing costs, bonus and loss of profit-earning capacity.
The challenge, head by head
| Claim head | NHAI’s attack | Why it failed |
|---|---|---|
| Inputs — Rs. 4,38,36,642 | Clause 70 price adjustment was the exclusive remedy | The award was for overrun-period costs under clauses 6.4, 12.2 and 42.2, net of Clause 70 receipts |
| Plant & equipment — Rs. 4,55,10,280 | Wrong pro-rata method, aged machinery | The tribunal rejected the higher alternative computation and awarded only claimed ownership cost; quantification is its domain (McDermott) |
| Overheads — Rs. 6,86,95,108 | No timely notice, no verifiable records, excessive | MoRTH Data Book rate of 11.64% less 15% mitigation held rationally supported (Batliboi) |
| Interest — 10% compounded monthly | Sub-clause 60.8 inapplicable; rate excessive | Within the tribunal’s power; no contractual contradiction shown |
The standard applied
The judgment works squarely within Ssangyong Engineering v. NHAI, (2019) 15 SCC 131: patent illegality and public policy, not appellate correction. The Court put the discipline plainly — “The question under Section 34 is not whether this Court would have reached the same findings.” On the Engineer’s contemporaneous rejection of the claims, it added a point of wider use: the Engineer’s view is material the tribunal must weigh, but “the Court must assess those reasons under Section 34, rather than treat the Engineer’s rejection as conclusive.” Finding the majority’s view plausible on every surviving head, it held: “The petition under Section 34 of the Act is accordingly dismissed” — the award stands unmodified, with no order as to costs.
What employers and contractors should note
Three practice points emerge. First, an unconditional extension of time is the single most consequential document in a prolongation dispute; employers who intend to contest causation should say so when granting it. Second, notice objections under clauses like 53.1–53.3 must be developed before the tribunal with specificity, because Section 34 review will not re-open them as fresh defences. Third, for contractors, the heads that failed — financing costs, bonus, loss of profitability — failed for want of proof, not of principle: the tribunal’s willingness to award formula-based overheads did not extend to speculative heads. Eleven years after the award, the money remains payable with compounding interest — a reminder that an unsuccessful Section 34 petition is often the most expensive filing in the file.
Frequently Asked Questions
What are prolongation costs?
Costs a contractor incurs because the works ran beyond the scheduled completion for reasons not attributable to it: extended deployment of plant and machinery, site and head-office overheads, and increased input costs over the overrun period. Here the scheduled completion was November 2008; actual completion came in December 2009, and NHAI granted the extension without penalty or liquidated damages.
Did the price-adjustment clause bar the input-cost claims?
No. NHAI argued that Clause 70’s price-adjustment formula exhausted the contractor’s remedy for cement, steel, bitumen and POL. The tribunal — and the Court — treated the claims as additional costs of the overrun period under other clauses, net of what Clause 70 had already paid, so NHAI v. Progressive-MVR did not assist.
How were overheads quantified?
The tribunal applied the MoRTH Data Book weighted rate of 11.64% and then cut 15% for mitigation, awarding Rs. 6,86,95,108. Following Batliboi v. HPCL and McDermott, the Court held the methodology rationally supported and quantification a matter for the tribunal.
Why did the interest award survive?
Interest at 10% per annum compounded monthly from 5 February 2011 — the invocation — was within the tribunal’s power, and NHAI could not show it contradicted the contract; the Court also noted its own line of authority reading sub-clause 60.8 as covering sums found payable by the tribunal.