Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Section 34 Challenge
Delhi High Court · 23 November 2026

Contra Proferentem Needs an Ambiguity First: DDA’s Section 34 Challenge Succeeds on the M-30 Cement Claims

The court sustains the tribunal’s findings on M-25 and M-35 concrete but sets aside the M-30 awards, holding that an express term covering “any grade of RCC” was ignored and a recovery rate was converted into a payment right.

In Delhi Development Authority v. B.G. Shirke Constructions Technology Pvt. Ltd. (O.M.P. (COMM) 361/2017 with 362/2017, decided 23 November 2026), Justice Om Prakash Shukla of the Delhi High Court partly allowed DDA’s challenges under Section 34 of the Arbitration and Conciliation Act, 1996 to twin 2017 awards in a dispute over cement content in prefabricated housing contracts for Narela and Rohini. The judgment is a clean illustration of the patent-illegality ground: an arbitral tribunal may interpret a contract, but it may not ignore an express term, reach for contra proferentem where no ambiguity exists, or award money on unexpressed notions of fairness.

Two clauses, one tension

The 2013 agreements for the Narela and Rohini prefab housing projects pulled in two directions. Clause 9.1.2 applied the CPWD Specifications and IS:456 minimum cement content — 330 kg/cum in the CPWD table. Clause 9.1.3 set a 360 kg/cum minimum for “any grade RCC” and prescribed recovery thresholds — levels below which DDA would deduct — for M-25 and M-35 concrete, saying nothing about a threshold for M-30. The contractor had flagged the tension at pre-bid stage; DDA answered that the NIT provision would prevail. During execution DDA directed design mixes with higher cement content (410 kg/cum for M-30), the contractor claimed the extra cost, and the tribunal awarded it in 2017.

Where interpretation ends and rewriting begins

The court’s framework is orthodox: a Section 34 court does not sit in appeal, and a plausible reading of a commercial contract is the arbitrator’s to make — but an award cannot add terms to the contract or rewrite it. Within that framework the two sets of findings met different fates.

FindingTribunal’s approachSection 34 result
M-25 / M-35 claimsRecovery thresholds in Clause 9.1.3 operate independently of the minimum-content stipulationsSustained — a plausible interpretation
M-30 baselineTook 330 kg/cum as the contractual minimum, applying contra proferentem against DDASet aside — the express words “any grade of RCC” (360 kg) were never examined; no ambiguity, so no occasion for contra proferentem
M-30 money awardsRs 3.16 crore for excess cement to mid-2015; Rs 6/kg thereafter; refund of recoveries; interestSet aside — no pleaded quantum meruit, no variation clause identified, and a deduction rate applied “in reverse” as a payment rate

The court added that, although not stated expressly, the tribunal appeared to have awarded the M-30 amounts on fairness or equity — impermissible without the parties’ authorisation under Section 28(2). The combination — ignoring an express term, creating an entitlement devoid of contractual or legal foundation — made the M-30 portions patently illegal.

The operative order

Both petitions were allowed in part. The awards stand set aside insofar as they fix the M-30 minimum at 330 kg/cum, award Rs 3,16,78,614 for excess cement in M-30 concrete up to 30 June 2015, direct payment at Rs 6/kg thereafter, direct refund of M-30 recoveries founded on the same reasoning, and award consequential interest. Everything else in the awards survives. No order as to costs.

Drafting and arbitration takeaways

• Pre-bid clarifications echo for a decade. The contractor’s pre-bid queries legitimised the tribunal’s examination of the clauses — but DDA’s “NIT prevails” answer also anchored the express-term argument that ultimately won.

• Contra proferentem is a tie-breaker, not an opener. It applies only after a genuine ambiguity survives harmonious construction.

• Plead the basis of the money claim. If the entitlement is quantum meruit or a variation, say so before the tribunal; a Section 34 court will not supply the foundation afterwards.

• Deduction clauses are not payment clauses. Rates fixed for recoveries cannot be mirrored into entitlements.

This report is based on the judgment as published. Section 34 outcomes are intensely contract-specific; nothing here is legal advice.

Frequently Asked Questions

What was the dispute about?

DDA’s contracts for over 31,000 prefabricated LIG and EWS units incorporated CPWD specifications and set minimum cement contents. One clause referenced CPWD/IS:456 minimums; another fixed 360 kg/cum for “any grade RCC” with recovery thresholds for M-25 and M-35. When DDA directed richer design mixes, the contractor claimed the cost of the extra cement, and the tribunal awarded it — including over Rs 3.16 crore for M-30 concrete.

Why did the M-30 findings fall while M-25/M-35 survived?

For M-25 and M-35, the contract’s recovery thresholds operated independently, and the tribunal’s reading was a plausible interpretation within its domain. For M-30, the tribunal fixed a 330 kg/cum baseline without examining the express words “any grade of RCC” in the 360 kg clause — which necessarily include M-30 — so there was no ambiguity to trigger contra proferentem, and the baseline ignored an express term.

What else was wrong with the M-30 award?

The court held there was no contractual or legal basis for the money: no quantum meruit was pleaded, no variation clause was identified for DDA’s richer-mix instruction, and the tribunal applied the contract’s Rs 6/kg recovery rate in reverse — turning a clause designed for deductions into a payment entitlement. An award resting on unexpressed fairness is impermissible absent authorisation under Section 28(2).

Does this widen Section 34 review?

No. The court restated that Section 34 is not an appeal and that plausible contract interpretation belongs to the arbitrator. The intervention rests on the narrow, settled categories: ignoring express terms, rewriting the bargain, and creating entitlements with no foundation — each a facet of patent illegality.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 29 November 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.