Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Arbitration: Section 34
Delhi High Court · 23 November 2026

Patent Illegality in a Lump-Sum Contract: The M-30 Cement Awards Fall

The tribunal’s reading of the cement clauses survived for two concrete grades but not the third: an award resting on “fairness” rather than a contractual term cannot stand under Section 34.

In Delhi Development Authority v. B.G. Shirke Constructions Technology Pvt. Ltd., O.M.P.(COMM) 361/2017 and 362/2017, decided on 23 November 2026, Justice Om Prakash Shukla of the Delhi High Court partly allowed DDA’s Section 34 petitions against awards dated 22 May 2017 in disputes from prefabricated housing contracts at Narela and Rohini. The award of Rs. 3,16,78,614 for excess M-30 cement, the Rs. 6/kg payment direction and connected refund and interest reliefs were set aside as patently illegal; the remaining findings survived.

A conflict written into the contract

DDA’s tenders for prefabricated RCC housing split the work into two groups, awarded in April 2013. Clause 9.1.2 tied minimum cement content to the CPWD Specifications 2009 and IS:456 — 330 kg/cum, with a maximum of 500. Clause 9.1.3 fixed 360 kg/cum for “any grade RCC” and set recovery thresholds of 410 kg (M-25) and 428 kg (M-35) — but none for M-30. The contractor flagged the conflict at both pre-bid meetings; DDA answered that the NIT provision would prevail. When DDA directed design mixes above 330 kg/cum in execution, the contractor claimed the extra cement cost, arbitration followed in 2015, and the tribunal — applying contra proferentem — treated 330 kg/cum as the baseline for all grades, awarding Rs. 3,16,78,614 for excess M-30 cement with a Rs. 6/kg rate going forward.

Where the award crossed the Section 34 line

Interpretation is the tribunal’s domain. The Court repeated that it “does not exercise appellate jurisdiction over an arbitral award”, and left the M-25 and M-35 findings intact as plausible readings of clauses 9.1.2 and 9.1.3.
But an express term cannot be overridden. For M-30, the tribunal had, in the Court’s words, overridden “the specific and unambiguous requirement of 360 kg per cubic metre expressly stipulated under Clause 9.1.3.”
No recovery threshold ≠ a right to payment. The absence of a right to recover from the contractor does not create a reciprocal right to be paid; the claim was never pleaded as quantum meruit, and no contractual provision supported it.
Equity needs authorisation. An award resting on fairness or equity is impermissible without the parties’ express authorisation under Section 28(2); an award that “ignores express contractual stipulations or re-writes the contract suffers from patent illegality under Section 34.”

The operative outcome

Both awards were set aside to the extent they: treated 330 kg/cum as the M-30 minimum; awarded Rs. 3,16,78,614 for excess M-30 cement up to 30 June 2015; directed payment at Rs. 6/kg thereafter; directed refund of M-30 recoveries resting on the same reciprocal-entitlement logic; and awarded consequential interest. Both petitions were allowed in those terms, the remaining findings — including on jurisdiction and the other grades — left undisturbed, with no order as to costs. The Court applied SEAMEC Ltd. v. Oil India Ltd., (2020) 5 SCC 164, on the limits of permissible construction.

Drafting and arbitration lessons

The dispute is a monument to an unresolved pre-bid query: both sides saw the clash between 330 and 360 kg/cum before contract, and a one-line clarification would have prevented a decade of litigation. For counsel resisting awards, the case illustrates the most reliable Section 34 ground in current practice — not re-arguing interpretation, but isolating the point where the tribunal stopped construing the contract and started supplementing it. And for claimants, it is a reminder that a claim without a clause must be pleaded for what it is — quantum meruit or damages for breach — because a tribunal cannot be left to source the entitlement in fairness after the fact.

Section 34 findings do not re-decide the commercial merits; they test the award against the grounds in the Arbitration and Conciliation Act, 1996. Case details are as recorded in the judgment dated 23 November 2026.

Frequently Asked Questions

What was the underlying dispute?

The 2013 contracts tied minimum cement content to CPWD Specifications (330 kg/cum) in one clause while another fixed 360 kg/cum for “any grade RCC” with recovery thresholds for M-25 and M-35 only. When DDA directed richer design mixes during execution, the contractor claimed the cost of cement above the minimum, and the tribunal awarded it for M-30 using contra proferentem.

Why did the M-30 award fail when the M-25 and M-35 findings survived?

For M-25 and M-35 the tribunal’s interpretation of the competing clauses was a plausible reading, which Section 34 protects. For M-30, the Court held the tribunal overrode the express 360 kg/cum stipulation and then built a payment right out of the absence of a recovery threshold — reasoning from fairness, not from any contractual term.

What is the significance of the contract being lump-sum?

In a lump-sum contract the contractor prices the risk of design mixes within the specified range — here 330 to 500 kg/cum under the CPWD specifications. As the Court put it, the parties are bound by the bargain they have struck; a tribunal cannot convert a recovery rate of Rs. 6/kg into a payment rate by applying it in reverse.

When can an arbitral award be set aside in part?

Where the offending findings are severable. The Court set aside only the M-30 minimum finding, the monetary award, the prospective payment direction, the linked refund and consequential interest, expressly leaving the remaining findings of both awards undisturbed.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 24 November 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.