In M/s Telecommunication Consultants India Ltd. v. M/s Rajput Construction, FAO (COMM) 152/2023, decided on 17 November 2026, a Division Bench of the High Court of Delhi comprising Justice Avneesh Jhingan (author) and Justice Shail Jain allowed a Section 37 appeal and remitted Section 34 objections to the Commercial Court — because the court below had set aside an award on the unilateral-appointment ground without first deciding the State entity’s objection that the challenge was time-barred.
The dispute’s long tail
TCIL won a tender of the Madhya Pradesh Rural Road Development Authority and sub-let the work back-to-back to Rajput Construction under an MOU of 18 October 2007. TCIL invoked arbitration on 7 April 2014; a sole arbitrator appointed unilaterally by TCIL passed an ex parte award on 15 May 2018. Rajput filed Section 34 objections on 27 May 2019, asserting it first received the award on 1 March 2019 through an RTI response. The Commercial Court set the award aside on 13 April 2023 on the unilateral-appointment ground — without deciding TCIL’s objection that the petition was time-barred.
The sequencing error
The Division Bench’s holding is about order of operations. Section 34(3) fixes a hard clock: three months from receipt of the award, with a grace period that is strictly capped — “The Court has the power to condone the delay only for a period of thirty days beyond the prescribed limitation period.” The general condonation power of Section 5 of the Limitation Act is excluded, a position settled through Consolidated Engineering, Singh Enterprises, Hongo India and Chhattisgarh SEB, all noticed in the judgment. A petition filed beyond three months and thirty days is dead on arrival, and nothing in it — however meritorious — can be examined.
That is why the Commercial Court’s approach could not stand: “The Commercial Court erred in not deciding the issue of limitation at the first instance.” The unilateral-appointment ground under Section 12(5) — powerful after the Supreme Court’s ineligibility jurisprudence — waits its turn behind the threshold question of when Rajput actually received the award, the fact on which the entire limitation computation hangs.
Receipt of the award: the fact that starts the clock
| Event | Limitation consequence |
|---|---|
| Delivery of a signed copy to the party (Section 31(5)) | Starts the three-month period; delivery to an agent or counsel can raise disputes about effective receipt |
| Knowledge of the award without delivery | Contested terrain — the challenger’s asserted date of receipt (here, an RTI response of 1 March 2019) must be tested on evidence |
| Three months from receipt | The primary window for filing Section 34 objections |
| Thirty further days on sufficient cause | The absolute outer limit; beyond it, no condonation at all |
Practice consequences
For award-holders, the judgment is a reminder to prove delivery meticulously — a signed copy served under Section 31(5), with acknowledgment — because a fuzzy delivery record hands the challenger its limitation argument. For challengers, the lesson is the mirror image: the date of receipt must be pleaded and provable, and the petition filed within the unforgiving window, since even a strong ineligibility ground cannot resurrect a late petition. The remitted proceedings, with appearance fixed for 14 December 2026, will decide the receipt question first.
Frequently Asked Questions
What is the limitation for a Section 34 challenge?
Three months from receipt of the award, extendable by a maximum of thirty days on sufficient cause shown — and no further. As the Court reiterated, the power to condone extends only to that thirty-day window; Section 5 of the Limitation Act stands excluded by the scheme of Section 34(3) read with Section 29(2) of the Limitation Act, on the line of authority from Consolidated Engineering through Hongo India.
Why does limitation come before the merits grounds?
Because a time-barred petition confers no jurisdiction to examine any ground, however attractive. The Court held the Commercial Court erred in not deciding limitation at the first instance: the Section 12(5) unilateral-appointment challenge can be examined only if the objections are within time.
What was the unilateral-appointment issue?
TCIL had appointed a sole arbitrator unilaterally, and the arbitrator passed an ex parte award on 15 May 2018. After the Supreme Court’s Section 12(5) jurisprudence, such appointments are vulnerable. But the respondent filed its Section 34 objections on 27 May 2019, claiming it first received the award on 1 March 2019 through an RTI response — making receipt of the award the contested fact on which limitation turns.
What happens now?
The Commercial Court’s judgment stands set aside and the Section 34 petition is remitted: the parties appear on 14 December 2026, the limitation objection is decided first, and only if the petition survives does the unilateral-appointment ground fall for decision — expeditiously, the award being of 2018 vintage.