Bar Council of India Notice

Disclaimer & Confirmation

As per the rules of the Bar Council of India, an advocate is not permitted to solicit work or advertise. By clicking “I Agree” below, you acknowledge and confirm that:

you are seeking information about Advocate Manish Jha of your own accord and for your own information and use; there has been no advertisement, personal communication, solicitation, invitation or inducement of any kind whatsoever from Advocate Manish Jha or the chamber to solicit any work through this website; the information made available here is provided only on your specific request; and no information on this website is to be construed as legal advice, nor does its use create any advocate-client relationship.

⚖  E-397, 4th Floor, Tagore Garden Extension, New Delhi – 110027 Mon–Sat  ·  +91 98738 50301  ·  legal@advocatemanishjha.com
Advocate Manish Jha Criminal · Civil · Family Law — New Delhi ☎  Consult the Chamber
Home › Arbitration: Section 29A
Delhi High Court · 6 November 2026

Award Reserved, Clock Expiring: A Consent Extension Under Section 29A

With proceedings concluded and the award awaited from a tribunal of three former judges, the court extended the mandate by eight weeks and regularised the intervening period.

In Meenambakkam Realty Private Limited v. Airports Authority of India (O.M.P.(MISC.)(COMM.) 864/2026, decided 6 November 2026), Justice Om Prakash Shukla of the High Court of Delhi extended the mandate of a three-member arbitral tribunal by eight weeks under Section 29A of the Arbitration and Conciliation Act, 1996. The proceedings had concluded and the matter stood reserved for award since May 2026; the tribunal’s office had indicated that the award needed a little more time. The respondent raised no objection, and the court also regularised any intervening period between expiry and extension.

The case in one view

CaseMeenambakkam Realty Pvt. Ltd. v. Airports Authority of India, O.M.P.(MISC.)(COMM.) 864/2026
CourtHigh Court of Delhi, Om Prakash Shukla J
Decided6 November 2026
ProvisionSection 29A, Arbitration and Conciliation Act, 1996
TribunalThree former judges, with the matter reserved for award since 28 May 2026
OutcomeMandate extended by eight weeks from the order; intervening period regularised

The application

The petitioner sought a further eight-week extension of the mandate of an arbitral tribunal comprising three former judges of the superior courts. The arbitration itself was at the very last stage: by a procedural order of 28 May 2026, the matter had been reserved for pronouncement of the award. In October 2026, a communication from the presiding arbitrator’s office indicated that the award required more time. Rather than let the mandate run out with the award unpronounced, the petitioner moved the court; the respondent’s counsel accepted notice and stated there was no objection.

From the order (para 5): “the mandate of the learned Arbitral Tribunal is extended for a further period of 8 weeks from today” — with any intervening period also regularised.

Section 29A in brief

Section 29A disciplines domestic arbitration with a statutory clock: twelve months from completion of pleadings, a further six by consent, and thereafter only court-sanctioned time. The provision was designed against the old culture of arbitrations that meandered for years; its cost is that even a well-run arbitration needs a court visit if the award cannot be delivered within the consented period. The courts’ working approach distinguishes between extensions sought to continue dragging proceedings and extensions sought to let a completed proceeding reach its natural end. This case sat firmly in the second category — everything was done except the pronouncement.

Practical sequence for parties

Track the clock from pleadings. Diarise the twelve-month mark and the consent extension; do not discover expiry from the opposite side’s objection.
Consent early. The six-month consent extension needs no court and should be recorded in a procedural order while time remains.
Move the court before expiry where possible. An application filed in time keeps the mandate alive pending disposal; if filed after, seek regularisation of the gap, as was granted here.
Keep it consensual at the award stage. Where the award is reserved, opposing an extension rarely serves either side — a lapsed mandate benefits no one and invites satellite litigation.

The takeaway

For commercial parties arbitrating in Delhi, this order is a clean illustration of Section 29A working as intended: a short, consent-based extension, granted in a two-page order, protecting months of completed hearings from a technical lapse. The discipline of the provision remains real — but where the only step left is pronouncement, the courts’ door is open, and the sensible course for both sides is to walk through it together.

Frequently Asked Questions

What is the Section 29A timeline for domestic awards?

The award in a domestic arbitration must be made within twelve months of completion of pleadings, extendable by six months with the parties' consent. Beyond that, the mandate continues only if a court extends it — on an application made before or after expiry — for sufficient cause and on such terms as the court imposes.

Is an extension easier when the award is already reserved?

As a practical matter, yes. Where hearings are over and only the pronouncement remains, refusing an extension would waste the entire proceeding and force a restart. In this case the court noted that the proceedings had concluded, the award was reserved, and both parties agreed — the extension of eight weeks followed without controversy.

What does "regularising the intervening period" mean?

Where the mandate lapses before the extension application is decided, acts done by the tribunal in the gap could be questioned. A direction regularising the intervening period protects the proceedings from that technical attack, treating the mandate as continuous through to the extended date.

Who can apply for the extension?

Either party may apply under Section 29A to the court. In practice, as here, the party interested in the award moves promptly once the tribunal signals that more time is needed, and a consent position between the parties makes the hearing short.

Note: This article is general information about the law and is not legal advice. It does not create an advocate-client relationship. The position stated is as at 10 November 2026 and may have changed since. Readers should verify any provision or decision referred to against the official text and seek advice on their own circumstances.