In M/s I Hub Express Pvt. Ltd. v. M/s Instakart Services Pvt. Ltd. (ARB.P. 1182/2025, decided 5 November 2026), Justice Prateek Jalan of the Delhi High Court appointed an arbitral tribunal through the Delhi International Arbitration Centre for a Delhi-registered micro enterprise whose delayed-payment reference had languished before the Facilitation Council. The respondent’s contract said arbitration seated in Bangalore, with exclusive jurisdiction to Bangalore courts. The court held that the statutory scheme of the MSMED Act, 2006 overrides both — jurisdiction follows the supplier’s location under Section 18(4), and the Council’s inaction does not leave the supplier remediless.
The familiar standoff: statute versus clause
A Delhi-registered micro enterprise provided logistics services under a 2019 principal agreement with addenda. Invoices went unpaid; the supplier filed a Section 18 reference before the Delhi Facilitation Council in September 2023. After one hearing that December, nothing happened — no conciliation scheduled, no arbitrator appointed. The supplier moved the Delhi High Court under Section 11(6) of the Arbitration and Conciliation Act. The respondent’s defence rested on the contract: clause 11.1 seated arbitration in Bangalore, and clause 11.2 gave Bangalore courts exclusive jurisdiction.
Why Delhi, not Bangalore
The answer lies in the MSMED Act’s architecture. Section 18(4) provides that the Facilitation Council of the place where the supplier is located has jurisdiction, and Section 24 gives Sections 15 to 23 overriding effect over anything inconsistent in any other law — including, as the Supreme Court held in Gujarat State Civil Supplies Corp. v. Mahakali Foods (2023) and reaffirmed since, a contractual arbitration clause. A buyer cannot contract its way out of the supplier-location rule. The petitioner being registered in Delhi, the Delhi High Court was the correct Section 11 forum, Bangalore clauses notwithstanding.
Council inaction is not a dead end
The subtler question was remedial: the MSMED route runs through the Council — conciliation under Section 18(2), then arbitration under Section 18(3). What happens when the Council simply does not move? Following Vallabh Corporation v. SMS India (Delhi) and the Bombay High Court in Microvision Technologies, the court held that a Section 11 application lies where the Council fails to refer the dispute to arbitration. On the facts, the Council had been seized of the reference since 2023 with nothing to show; court-annexed mediation during the petition itself ended “Not-Settled” in February 2026; and the respondent — which never appeared at the final hearing — had not used an earlier liberty to mediate. The prematurity objection failed.
Jurisdiction at the supplier’s location — the contract cannot shift it.
Overriding effect: the MSMED scheme prevails over inconsistent contractual terms.
The court’s appointment power fills the gap when the Council stalls.
Institutional arbitration, panel nomination, Section 12 disclosures.
Practice notes for MSME suppliers — and buyers
• Suppliers: registration details matter. The Udyam registration and the supplier’s registered location anchor both Council jurisdiction and, as here, the Section 11 forum. Keep a dated record of the Council filing and every hearing — the timeline of inaction is the foundation of the court petition.
• File the contract. The court pointedly criticised the petitioner for omitting the principal agreement from the petition. The arbitration clause must be placed before the court even when the argument is that the statute overrides it.
• Buyers: an exclusive-jurisdiction clause is not a shield against the MSMED machinery. The realistic battlegrounds are supplier status, the supply’s coverage under the Act, and the merits — all of which remain open before the arbitrator.
Frequently Asked Questions
Why did the Bangalore arbitration clause not apply?
Following Gujarat State Civil Supplies Corp. v. Mahakali Foods and subsequent authority, the court held that Section 18 of the MSMED Act, being a special statutory dispute-resolution mechanism with overriding effect under Section 24, prevails over a contractual arbitration clause. Section 18(4) vests jurisdiction in the Facilitation Council where the supplier is located — here, Delhi — so the Delhi High Court was the right forum for the Section 11 petition.
Can a supplier go to court while the Council reference is pending?
Where the Council fails to act on a Section 18 reference for a long period — here, no mediation was scheduled and no arbitrator appointed for years after the 2023 filing — the court held, following Vallabh Corporation and the Bombay High Court’s view in Microvision Technologies, that a Section 11 application lies. The statutory process cannot become a dead end through administrative inaction.
Did the supplier have to complete conciliation first?
The respondent argued the reference was premature because Section 18(2) conciliation had not run its course. The court rejected this: the supplier had filed in 2023, the Council did nothing, and mediation attempted during the court proceedings ended in a “Not-Settled” report. The conciliation requirement cannot be weaponised by inaction.
What did the court finally order?
Disputes under the agreement were referred to arbitration under the aegis of the Delhi International Arbitration Centre, which will nominate an arbitrator from its panel under its rules, with the required Section 12 disclosures. All contentions — including arbitrability and maintainability — were left open before the arbitrator.